Bellerive Oval Tasmania

Application: Standby Emergency Power     Download Power Profile


BACKGROUND

The 2009-10 Cricket season represents a major milestone for the Tasmanian Cricket Association following
confirmation in April 2009 that the Tasmanian State Government would provide funding for the installation of
television standard lighting at Bellerive Oval.

Tasmania had been under pressure to install lights at the oval for some time with television broadcasters
serving notice that future national and international telecasts needed to be day/night fixtures.


POWER NEEDED

Chubb Fire and Safety Tasmania were one of the successful tenderer for the project and according to Chubb’s Contract Supervisor, Troy Sharp, the pressure was on from day one to have the project designed, built and up-and-running for the start of the 09/10 Cricket season.

“Our involvement centred on the installation of the four 45 metre light towers, the 11 metre head-frames and the
associated reticulation works that included two new main switchboards and two standby gen-sets.

“The light towers were made in two sections and lifted into place by a 160 tonne crane and made ready for the lighting head-frames to be attached.

“Power for the lighting head-frames which house over 108 light fittings that each require 2 kW of power comes onto site from Aurora Energy’s power grid, but due to Occupational Health and Safety regulations we had to
provide enough emergency back-up power to run 7 fittings per tower in order to produce roughly 100 lux of
light to enable the public to egress from the ground safely in the event of a mains failure.

“For the standby power requirements the emergency lighting design called for two units, a 150 kVA unit to feed
the north tower and a 220 kVA unit to feed the three southern towers plus the oval’s pole mounted emergency lighting system. 


SOLUTION

“Selection of the most suitable gen-sets for the project was based on three major considerations which included price, reliability and availability and all the leading brands were considered.

“In the end Caterpillar’s Olympian GEP 150 and GEH 220 gen-sets best met the criteria, plus they came with the backing of local Cat® dealer William Adams who we’ve had a fair bit to do with over the years and have always found them to be extremely competent in the support of their Caterpillar products.

“Because of the extensive design work involved in the project the eventual lead-time for supplying the gen-sets was very tight, but William Adams worked closely with their associate company Energy Power Systems to ensure the Olympian gen-sets were available when we needed them.

“And when we were ready the guys from William Adams were able to get the gen-sets on site and commission them in just two days enabling us to get the project completed in December, which was well before the specified
deadline.


RESULTS

“Following installation the Olympian gen-sets have lived up to our expectations and performed faultlessly in all
the trials, with their ratings easily handling the load requirements of the lights while giving us some additional capacity for any future requirements,” Troy said.

Commenting on the Bellerive Oval project, Roger Davey from Energy Power Systems Australia (EPSA) said that the seamless service provided to Chubb was a reflection of the excellent working relationship EPSA has with its Cat dealer partners throughout Australia.

“William Adams briefed us on the project in June and Chubb placed the order in September. Being able to supply the generator sets ex-stock gave us sufficient time to customise the order to include jacketed water heaters and sound attenuated enclosures at our facility in Hallam, then load test them prior to delivery to Chubb in November.

“Following installation on-site William Adams handled the start-up commissioning and will subsequently look
after the Olympian generator’s parts and servicing requirements.

“Olympian generators represents a lower cost entry level product range that are manufactured at Caterpillar’s
ISO 9001certified facility in the UK and boast Caterpillar’s legendary performance, exceptional fuel efficiency
and proven performance for standby and prime power applications up to 550 kVA.

“Available for use with diesel fuel, propane, or natural gas, Olympian generator sets deliver dependable, clean
and economical power even in the most demanding conditions and can be configured by Energy Power Systems Australia to meet the needs of any application and then support it nationwide through EPSA’s and Caterpillar’s extensive service network.

“Energy Power Systems Australia is proud that Olympian generator sets were chosen to provide the standby power requirements for such a famous ground that is now a fully fledged international venue,” Roger said. 

For more information on the extensive range of Olympian generator sets contact us on 1800 800 441 or visit www.olympiangenerators.com.au


ABOUT CATERPILLAR

For more than 80 years, Caterpillar Inc. has been making progress possible and driving positive and sustainable change on every continent. With 2007 sales and revenues of $44.958 billion, Caterpillar is a technology leader and the world’s leading manufacturer of construction and mining equipment, clean diesel and natural gas engines and industrial gas turbines. 

Innovation place

It’s lights on at Bellerive Oval

CUSTOMER

Bellerive Oval Tasmania.

LOCATION

Tasmania

BACKGROUND

Cricket Australia’s broadcast partners advised the Tasmanian Cricket Association that unless lights were installed at Bellerive Oval they would not be able to allocate the Oval any One-day International or Twenty20 matches beyond the 2008-9 cricket season.

SOLUTION

Following an allocation of funding from the Tasmanian State Government, Chubb Fire & Safety were awarded the contract to install four 45 metre light towers complete with 11 metre lighting head-frames, new main switchboards and associated reticulation work.

To comply with OH&S requirements, Chubb Fire & Safety chose two Olympian generator sets to provide back-up power to run 7 light fittings per tower to enable the public to exit the ground safely in the event of a mains failure.

PRODUCTS

Three phase Olympian GEP150 and GEH220 generator sets in sound attenuated enclosures rated at 150 kVA and 220 kVA respectively.

FURTHER INFORMATION

CALL: 1800 800 441

www.olympiangenerators.com.au


STANDBY EMERGENCY POWER

Lake Mountain Resort - Olympian generator

The Chubb Fire & Safety team use a 160 tonne
crane to lift one of four 11 metre lighting
head-frames into place.


About Energy Power Systems Australia

Energy Power Systems Australia is Australia’s specialised Caterpillar engine dealer, supplying Australia and Papua New Guinea with the world’s finest power systems.

We provide Caterpillar engines and systems for virtually any application, from road and marine to power generators and compressors, if it’s Caterpillar, then Energy Power Systems Australia is right behind it.

Through our network of offices across Australia and Papua New Guinea, our people give comprehensive engineering support and technical advice to the Caterpillar Engine community.

When it comes to powering your business, only Energy Power Systems Australia can deliver this combination of technically superior Caterpillar engines and unmatched technical and after-sales support. 

For more information on Caterpillar’s diesel generator sets, from 11 to 16,200 kW, or gas-powered generator sets from 100 to 6,000 kW:

Contact Energy Power Systems Australia on

1800 800 441, or visit: www.energypower.com.au